Official ANTAQ data up to 02/2026
Waiting time to berth at the Ferro Gusa terminal — Vitória (ES)
In the 12 months to 02/2026, vessels waited a median of 6.8 h to berth at the Ferro Gusa terminal, Vitória (ES); 1 in 10 waited more than 140.4 h (P90). Based on 42 recorded berthings. Source: ANTAQ — Estatístico Aquaviário.
The median wait is 211% above the national median for all cargo (2.2 h).
Port complex: Vitória
Last 12 months (to 02/2026)
- Waiting time to berth — Median
- 6.8 h
- Waiting time to berth — P90
- 140.4 h
- Berthings
- 42
- Operation
- 51.7 h
| Month | Median | P90 | Berthings |
|---|---|---|---|
| 02/2026 | insufficient data | insufficient data | 3 |
| 01/2026 | 18.6 h | 200.5 h | 5 |
| 12/2025 | insufficient data | insufficient data | 2 |
| 11/2025 | insufficient data | insufficient data | 3 |
| 10/2025 | insufficient data | insufficient data | 3 |
| 09/2025 | insufficient data | insufficient data | 3 |
| 08/2025 | 11.7 h | 94.4 h | 5 |
| 07/2025 | insufficient data | insufficient data | 4 |
| 06/2025 | insufficient data | insufficient data | 2 |
| 05/2025 | insufficient data | insufficient data | 3 |
| 04/2025 | 6.6 h | 137.3 h | 8 |
| 03/2025 | insufficient data | insufficient data | 1 |
How to cite
The data may be reused under the CC BY 4.0 license, citing the source:
Vessel Planner (LOGMAPS), based on ANTAQ data — Estatístico Aquaviário, 02/2026. https://logmaps-vessel-planner-prd.web.app/en/portos/vitoria/terminais/ferro-gusa
Source: ANTAQ — Estatístico Aquaviário, data up to 02/2026