Official ANTAQ data up to 02/2026

Waiting time to berth at Terminal Integrador Portuário Luiz Antonio Mesquita - TIPLAM (SP) — Dry bulk

In the 12 months to 02/2026, dry bulk vessels waited a median of 132.7 h to berth at Terminal Integrador Portuário Luiz Antonio Mesquita - TIPLAM (SP); 1 in 10 waited more than 413.9 h (P90). Based on 322 recorded berthings. Source: ANTAQ — Estatístico Aquaviário.

The median wait is 2,326% above the national median for dry bulk (5.5 h).

Last 12 months (to 02/2026)

Waiting time to berth — Median
132.7 h
Waiting time to berth — P90
413.9 h
Berthings
322
Operation
59.3 h
Median and P90 wait for dry bulk at Terminal Integrador Portuário Luiz Antonio Mesquita - TIPLAM, by month
MonthMedianP90Berthings
02/2026162.8 h490.6 h16
01/2026100.1 h379.0 h19
12/202573.7 h275.7 h30
11/2025150.2 h590.6 h28
10/202591.7 h290.5 h29
09/2025118.5 h418.4 h30
08/2025119.1 h355.9 h29
07/2025173.1 h360.0 h27
06/2025130.1 h517.4 h32
05/2025140.0 h245.9 h33
04/2025116.1 h274.2 h24
03/2025277.0 h535.3 h25

How to cite

The data may be reused under the CC BY 4.0 license, citing the source:

Vessel Planner (LOGMAPS), based on ANTAQ data — Estatístico Aquaviário, 02/2026. https://logmaps-vessel-planner-prd.web.app/en/portos/terminal-integrador-portuario-luiz-antonio-mesquita-tiplam/granel-solido

Source: ANTAQ — Estatístico Aquaviário, data up to 02/2026